Salient Features of Payra 1320MW Thermal Power Plant Project (2nd Phase)

Name of the Project Payra 1320 MW Thermal Power Plant Project (2nd Phase)
EPC Contract Signing 16.05.2019
EPC Contractor Consortium of CECC & NEPC, China
PPA & IA Signing 01.06.2021
Project Financer CEXIM Bank
Physical Progress 21%
Plant Capacity 1320 MW (2X660 MW)
Boiler Technology Ultra-supercritical (27 Mpa/600/610c)
Cooling Water System Closed circulation of water using cooling tower
Power Evacuation 400KV GIS Substation
Primary Fuel Imported Coal
Expected COD 3rd Unit: 24 months after Financial Closing
4th Unit: 30 months after Financial Closing
Overall Progress 1. Soil Investigation and Land Improvement work has been completed.
2. Test piling has been completed.
3. Detail design is going on.
4. Construction of water intake forebay is completed.
5. Water treatment system has been completed.
6. Construction of One Coal dome for Phase-2 has already been completed.
7. Jetty Extension work completed.
8. Central Mosque construction is going on.